Views: 0 Author: Site Editor Publish Time: 2026-11-18 Origin: Site
Choose a dedicated ridge cap roll forming machine when the same ridge section keeps coming back and you can supply the flashings that ship with it. Choose a long folder when the bends change across orders and one machine can handle the mix.
Test the choice against a shipment with a firm packing date. A finished batch of ridge caps earns you little extra time if the last flashing is still waiting for a machine.
Lay the ridge drawings side by side before you total the monthly metres. Mark what changed between revisions. A longer part affects where you cut and collect it. A different cross-section can change the tools you need.
Count repeat work by drawing and material. Two caps sold under the same part name may need different setups if their edge details or stock differ.
The two machines take different starting stock. The former guides coil strip through its rolls. The folder locates a sized blank against a backgauge, clamps it and bends the free edge with a folding beam.
| Decision factor | Dedicated ridge former | Long folder |
|---|---|---|
| Profile variability | One approved cross-section per fixed setup. Ask how variants are tooled. | Multiple straight-bend shapes within clamp, tool and capacity limits. |
| Batch pattern | Recurring releases of the same ridge section. | Mixed trim runs or repeat work that fits the available folder time. |
| Tooling | Section-specific rolls and compatible cutoff tooling. | Clamping and folding tools, bend programs and clearance for each bend. |
| Feeding | Coil strip wide enough for the full section, with a guide suited to that strip. | Sized blanks presented to the backgauge and clamp. |
| Cutoff | A post-cut line shears the formed profile to length. | Blank length is set before folding. Assign length cutting and width slitting. |
| Handling | Coil loading and support along the straight exit path. | Blank staging, support during bends and clearance to turn or unload long parts. |
Check cutting direction on the folder bid. A slitter that trims the width of a blank may still leave you to make the crosscut that sets its length. If your own shear makes that cut, include its time in the order schedule.
Pick a busy week and list the release time, drawing revision, material, pieces by length and packing deadline for each order. You can group two releases only if they share a setup and the earlier shipment can wait.
| Purchase choice | Where the work goes | What could hold the shipment? |
|---|---|---|
| Buy the long folder | Schedule blank cutting, each bend program and the first-piece checks on your actual shift. Try moving the ridge earlier. | If moving the ridge displaces the first flashing, one order still misses the last slot. Record the missing part and the delay. |
| Add a former and keep your folder | Run the repeat ridge on the former. Reserve the folder’s last slot for the late flashing. | Count coil loading and unloading. Two free machines can still be waiting for the same operator or packing bench. |
| Buy the former as your only machine | Send each flashing to a named subcontractor or another available machine. Get a confirmed delivery date. | Include transport and incoming inspection. If the flashings arrive on Thursday, a ridge ready on Tuesday cannot save Wednesday’s shipment. |
Replay an ordinary week as well. Use measured times where you have them and label estimates. Count accepted pieces of each drawing at packing. This shows whether the clash recurs often enough to affect your choice.
Follow your longest part from stock to packing on each layout. Mark where it rests, which way it travels and where it crosses another job. Ask who clears the station while the next piece is ready.
BMS lists its Metal Roof Ridge Cap Roll Forming Machine as the Philippines model for galvanized coil and prepainted galvanized steel (PPGI). The listing describes a manual pre-cutter and hydraulic cutting after forming. Folding requires a separate equipment proposal.
Ask each bidder to mark every item as included, optional or supplied by your factory. Price both routes up to the same accepted, packed part. An unpriced rack or outside cut still has to be provided.
Give both equipment suppliers the same ridge drawing, a difficult trim drawing and an order list. Ask which drawings their quoted machine can make and which tools the bid includes. Obtain separate prices and lead times for subcontracted parts.
Put the finished length and permitted deviation in mm on the drawing. Agree where to measure after cutoff or folding. Use your specified stock for the sample because the angle can change when the tools release the part.
Check wing widths, the finished angle and fit at both ends. Inspect the cut edge and coated face before accepting the sample. Ask each supplier to identify any finishing step your factory must still carry out.
Choose the former if the ridge repeats and every other trim has a dependable route to packing. Choose the folder if it covers the mix on time. When both pass, compare the annual cost of shipping the same orders.
Ask BMS for a dedicated ridge cap proposal. Send the ridge drawing, trim list, material and thickness, monthly quantities, cut lengths and current equipment. Request itemized tooling, cutting and handling. Use the same inputs for a separate long-folder proposal.